# New legislation for renovations in the UAE

Author: Hilda van der Tuin LLM
Published: 2026-07-20
Language: en
Source: https://www.holland-legal-services.ae/article-pages/en/1012-new-legislation-for-renovations-in-the-uae.html

If you have an apartment or villa renovated in the UAE, new statutory rules have applied to the agreement with your contractor since 1 June 2026. Federal Decree-Law No. 25 of 2025, the new Civil Transactions Law, has replaced Federal Law No. 5 of 1985.

The new rules do not only apply to large construction projects between developers and construction companies, but also to a private client who has a contractor do painting work, build a swimming pool, knock down a wall, replace the air conditioning, etc. And also to the company that has the interior of its new premises done.

### When is the other party a contractor?

The other party is a contractor if it undertakes towards you to make something or to carry out certain work in return for payment. A contractor therefore does not have to be a large construction company that puts up an entire building. A renovation company, fit-out company, kitchen company, installation company or self-employed tradesman can also be a contractor for the purposes of this law.

The name at the top of the agreement does not matter. The contract may, for example, be called a _renovation agreement_, _fit-out contract_, _works contract_, _service agreement_, _quotation_ or _proposal_. What is decisive is which work the other party has undertaken to carry out for payment.

The contractor may only carry out the work, while you buy and provide the materials. The contractor may also supply the work and all or part of the materials. Both fall under the statutory rules on contracts for work.

You must of course always first check whether the contractor you are working with actually has a licence, and you can do that, for example, via this register: [Consultants and Contractors Licensing Standards.](https://www.dm.gov.ae/municipality-business/consultants-and-contractors-licensing-standards/)

### Different contractors for one renovation

You can conclude separate agreements with several contractors for one renovation. Each contracting party can then be a contractor for its own work.

If you only conclude an agreement with one renovation company and that company itself brings in the tiler, electrician and plumber, the renovation company is your contractor. The other companies are subcontractors of the renovation company.

The contractor may have the work carried out in whole or in part by subcontractors, unless the agreement prohibits this or it follows from the nature of the work that the contractor must carry out the work himself. **The contractor with whom you concluded the agreement remains responsible towards you for the work of his subcontractors.**

So the contractor cannot wriggle out of it by saying that the defective tiling, the leak or the fault in the electrical installation was caused by a subcontractor, although he will of course try.

### What should a contract with a contractor contain?

-   who applies for the renovation permission or the NOC;
    
-   which documents are needed for that;
    
-   who supplies drawings and technical documents;
    
-   who pays the application costs;
    
-   who pays the deposit;
    
-   who is responsible for delays in the application;
    
-   on which date the work starts;
    
-   which working hours apply;
    
-   what will be demolished and what will remain standing;
    
-   which requirements apply to access for staff and materials;
    
-   who pays for any damage to common areas;
    
-   who applies for the final inspection after completion.
    
-   what exactly the agreed work involves;
    
-   what the nature and scope of the work is;
    
-   how the work is to be carried out;
    
-   within which period the work must be finished;
    
-   what you have to pay for the work.
    
-   where walls will be removed or put up;
    
-   what happens to pipes and electricity;
    
-   which floor, tiles, sanitary fittings and kitchen will be supplied;
    
-   which brands, materials, colours and dimensions have been chosen (only naming Elie Saab sanitary ware in the agreement is not sufficient);
    
-   who makes the designs and technical drawings;
    
-   who applies for the required permission from the building management;
    
-   who applies for permits or approvals from government authorities;
    
-   how the payment is divided;
    
-   how changes and extra work are approved;
    
-   how handover and inspection take place;
    
-   within which period defects must be repaired.
    

Annexes such as drawings, photos, material lists, quotations and a bill of quantities must be clearly identified as part of the agreement. Otherwise a discussion arises about whether a document was only provided for information or forms part of the agreement.

### Now suppose the pot of money is empty, or your husband cannot stand the mess any more and wants a divorce

Under the new law you may terminate the agreement and stop further performance of the work before the renovation is completed. The contractor does not have to have done anything wrong for that.

Under the old Civil Transactions Law there was no express general right to stop the contract for work for such reasons. The new law has now expressly included this right in article 836. You must then of course pay. You then have to cough up for the costs the contractor has incurred for the work; the work that has already been carried out; the profit the contractor would have made if he had finished the entire work.

The contractor must be able to prove that he really incurred these costs and that they relate to your renovation. A profit margin may already be included in the value of completed work. The same profit may not be claimed again as lost profit.

To calculate the lost profit, one can look at:

-   the price of the remaining work;
    
-   the costs the contractor would still have had to incur;
    
-   the profit margin included in the agreement or budget;
    
-   the costs saved by the termination;
    
-   income the contractor has earned with other work because time became available.
    

The court may reduce the compensation for lost profit. In doing so the court must take into account the costs the contractor no longer has to incur because the work was stopped and the income he has been able to earn from replacement work.

Article 836 therefore does not mean that the contractor is automatically entitled to the full remaining contract price. He is entitled to payment of his demonstrable costs, the value of the work carried out and the profit he would have earned on completion, less relevant savings and income from other work.

### Now suppose your contractor has sent a bunch of clowns your way

If you want to terminate the agreement because the contractor delivers defective work, does not turn up, fixes your air conditioning with chewing gum (no joke), causes serious delay or refuses to perform his obligations, the rules of article 818 also apply.

The contract must therefore make a clear distinction between:

-   termination because you do not want to continue with the project;
    
-   termination because of a failure by the contractor;
    
-   termination because performance has become impossible;
    
-   termination with the consent of both contracting parties.
    

That distinction matters for the question:

-   which amounts still have to be paid;
    
-   whether the contractor is entitled to lost profit;
    
-   whether you can recover repair costs;
    
-   whether you can claim damages;
    
-   what happens to advance payments already made;
    
-   what happens to materials and orders;
    
-   who bears the costs of a replacement contractor.
    

### Damages for delay agreed in advance

Renovation agreements can provide that the contractor must pay a certain amount if the work is delivered late. It can, for example, be included that the contractor owes AED 5000 per day from the agreed completion date, up to a maximum of ten per cent of the contract price.

Such a penalty clause is not completely untouchable. The court can adjust the amount under certain conditions. If your fault weighs considerably more heavily than the contractor's fault, the court may even decide not to award any damages.

If you want to receive more damages than the amount fixed in advance in the agreement, you must, under article 340, prove that the contractor committed fraud or made a gross error. An arrangement that conflicts with article 340 is invalid. The agreement therefore cannot exclude the court's statutory power to review the amount.

### The agreed amount is not an automatic payout

Even if the agreement names an amount per day, it must be examined:

-   whether the agreed completion date was binding;
    
-   whether the contractor was actually late;
    
-   whether a valid extension of the period for performance was agreed;
    
-   who caused the delay;
    
-   whether you as the client contributed to the delay;
    
-   whether the contractor completed part of the work on time;
    
-   whether the agreed damages are excessively high;
    
-   whether the contract names a maximum amount.
    

The contractor can therefore not be held liable solely on the basis of the agreed date without an investigation into the causes of the delay.

During the project you must therefore carefully keep:

-   the original schedule;
    
-   later revised schedules;
    
-   messages about delays;
    
-   requests for access;
    
-   choices of materials;
    
-   approvals of changes;
    
-   proof of payment;
    
-   correspondence with the competent building manager;
    
-   the renovation permission/the NOC;
    
-   proof of the date on which the contractor was given access to the building;
    
-   photos of progress;
    
-   reports of inspections and handovers.
    

### A fixed price stays fixed

Article 829 deals with an agreement in which a design or description of the work has been agreed for one fixed total price.

If the contractor has, for example, agreed to renovate your apartment completely for AED 300,000, he cannot suddenly increase that price because:

-   building materials have become more expensive;
    
-   his staff's wages have risen;
    
-   subcontractors are charging higher prices;
    
-   transport costs have risen;
    
-   he has budgeted the work incorrectly;
    
-   his other costs are higher than expected.
    

Article 829(1) expressly provides that rising prices of materials, higher staff costs and other increased costs of performance do not give an automatic right to a price increase where there is a fixed contract price.

### Extra work and changes

There is of course a lot of wrangling about extra and reduced work.

Article 829(2) provides that, where the design is changed or added to, the contractor is not automatically entitled to a higher payment.

The contractor may, however, be entitled to more money if:

-   the change or addition is necessary because of a fault attributable to you; or
    
-   you gave consent for the change and reached agreement with the contractor on the price increase.
    

Merely giving consent to carry out something different is therefore not the same as agreeing to any amount the contractor names later.

If during the renovation you have, for example, a wall moved, different tiles laid or an extra bathroom built, the following must be recorded in writing:

-   what is being changed;
    
-   what the extra work is;
    
-   which original work will no longer be done;
    
-   what the extra or lower amount is;
    
-   whether the amount is fixed or still to be calculated;
    
-   what the consequences are for the completion date;
    
-   whether the change affects other work;
    
-   whether an amended drawing is needed;
    
-   whether an amended NOC or an additional permit is needed.
    

The contractor should not first carry out the extra work and only then send an invoice that was not discussed in advance. You, in turn, may not simply assume that a change will be carried out free of charge if it clearly requires extra labour or material.

### A fault on your part

Article 829(2) also gives the contractor a possible claim to extra payment if the change is necessary because of a fault attributable to you.

That may be the case if you:

-   provided incorrect technical information;
    
-   gave incorrect measurements;
    
-   want or need to have a design you supplied adjusted;
    
-   supplied materials that turn out to be unusable;
    
-   did not provide necessary information in time;
    
-   had work started before the required renovation permission had been obtained;
    
-   did not pass on the conditions of the NOC to the contractor.
    

The law does not lay down a fixed calculation of how high the additional payment is in such a situation. The outcome depends on the agreement, the cause, the proven costs and the connection between your fault and the extra work.

### Exceptional general circumstances

Article 829(3) contains a separate rule for general exceptional circumstances that could not be foreseen when the agreement was concluded.

These must be circumstances that disturb the financial balance between you and the contractor and undermine the financial basis of the agreement.

The court can then, after weighing the interests of both parties:

-   extend the period for performance;
    
-   increase the contract price;
    
-   reduce the contract price;
    
-   terminate the agreement.
    

This does not mean that every increase in costs gives the contractor a right to a higher price. The contractor must prove that there are general and exceptional circumstances that could not be foreseen when the contract was concluded and that have seriously disturbed the financial balance. The rule can also work in your favour. The court may, after all, also reduce the payment if exceptional circumstances have changed the financial balance to your disadvantage.

An incorrect calculation, a disappointing profit margin or a normal price increase does not automatically fall under this; a war possibly does. One must then look at

-   the date on which the agreement was concluded;
    
-   the circumstances already known at that time;
    
-   the duration of the renovation;
    
-   the provisions on price increases;
    
-   which contracting party bears the risk concerned;
    
-   the actual financial consequences;
    
-   the measures the contractor could have taken.
    

The court, and not the contractor alone, has the power under article 829(3) to restore the "contractual balance".

### The contractor must warn you immediately

Article 816(3) contains a statutory duty for the contractor to warn.

The contractor must inform you immediately if during the work:

-   defects arise or become visible in materials you supplied; or
    
-   other circumstances arise that prevent proper performance of the work.
    

If the contractor does not do so, he is liable for the consequences of failing to give that warning. The contractor must, for example, warn you if he discovers that:

-   tiles you bought are cracked or unsuitable;
    
-   the sanitary ware you chose does not fit the existing connections;
    
-   a wall is constructed differently from what is shown on the drawings;
    
-   pipes are seriously damaged;
    
-   damp or mould is obstructing further work;
    
-   the electrical installation is unsafe;
    
-   a material is unsuitable for the humidity or temperature ;
    
-   the required renovation permission or the NOC is missing;
    
-   a design is technically not feasible;
    
-   the work cannot be continued in the agreed way;
    
-   additional permission from a government authority is needed.
    

So the contractor may not, without warning, carry on with work that he knows is defective, unsafe or not feasible and later throw the consequences over the fence to you.

### What can you do about defective work?

Article 818 provides that the contractor must carry out the work in accordance with the agreement and within the agreed period.

If the agreement does not contain a clear method of performance or period, the contractor must work in accordance with recognised technical standards and complete the work within a period that is reasonable for that kind of work.

If during the renovation you see that the contractor is working defectively or deviating from the agreement, you can require him in writing to repair the defect within a reasonable period.

Your notice must describe specifically:

-   what has been done wrongly;
    
-   which drawing, choice of material or agreement has been departed from;
    
-   what must be repaired;
    
-   within which period the repair must take place;
    
-   what you will do if the repair is not made.
    

If the contractor does not repair the work within the period set, then after the facts have been established you can:

-   request termination of the agreement; or
    
-   engage another contractor to finish or repair the work, at the expense of the first contractor.
    

The wording “after the facts have been established” means that you must properly record the condition and the defects before another contractor removes or repairs everything.

That can be done, for example, with:

-   clear photos and videos;
    
-   a written inspection report;
    
-   an engineer's report;
    
-   quotations for repair;
    
-   correspondence with the contractor;
    
-   an overview of the contractual specifications;
    
-   proof of the repair period granted.
    

### Immediate termination

You do not always have to give a repair period first.

Article 818(3) names situations in which immediate termination can be requested. That is possible, among other things, if:

-   repair is impossible;
    
-   repair is no longer compatible with the agreement;
    
-   the contractor starts so late or has caused so much delay that timely completion is no longer achievable;
    
-   the contractor's conduct shows that he does not intend to perform his obligations;
    
-   the contractor has made performance impossible.
    

Whether immediate termination is justified depends on the seriousness of the facts.